Optimal dates in Planned Order

Former Member
0 Kudos

Situation is following:

It is necessary to plan thus order terms Final Assemble that terms of planned orders of subordinate products were as it is possible more close to a date of issue Assembles 2,3,4

In an ideal should be so:

Hierarchy Final Assemble

Final Assemble --

Assemble 2 --

Assemble 3 Assemble 4

Ideal dates:

Final Assemble

BasicDates Ord.finish 11/3/2011

BasicDates Start 10/31/2011

Assemble 2

BasicDates Ord.finish 10/31/2011

BasicDates Start 10/23/2011

Assemble 3

BasicDates Ord.finish 10/23/2011

BasicDates Start 10/22/2011

Assemble 4

BasicDates Ord.finish 10/23/2011

BasicDates Start 10/21/2011

It becomes, that by the time of Plnd open. dates materials for a Product have been already bought, and subordinate knots are collected

It becomes that materials for assemblage in a warehouse didn't stand idle

How it is possible to reach desirable result?

What heuristics is better for using?

What is the strategy?

What options in a product should be?

What options of Optimizer?

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member197994
Active Contributor
0 Kudos

Hi Timofey,

There is the operation lead-time offset in BOM details when you can control the offset for the component in relation to the start date for production of the superior assembly. Best regards/Tiemin

Former Member
0 Kudos

//There is the operation lead-time offset in BOM details when you can control the offset for the component in relation to the start date for production of the superior assembly.

It`s doing in BOM of ERP or PDS(PPM) of APO?

former_member197994
Active Contributor
0 Kudos

Hi Tim,

First you find it in ECC and it can be transferred to APO. Best regards/Tiemin