Situation is following:
It is necessary to plan thus order terms Final Assemble that terms of planned orders of subordinate products were as it is possible more close to a date of issue Assembles 2,3,4
In an ideal should be so:
Hierarchy Final Assemble
Final Assemble --
Assemble 2 --
Assemble 3 Assemble 4
Ideal dates:
Final Assemble
BasicDates Ord.finish 11/3/2011
BasicDates Start 10/31/2011
Assemble 2
BasicDates Ord.finish 10/31/2011
BasicDates Start 10/23/2011
Assemble 3
BasicDates Ord.finish 10/23/2011
BasicDates Start 10/22/2011
Assemble 4
BasicDates Ord.finish 10/23/2011
BasicDates Start 10/21/2011
It becomes, that by the time of Plnd open. dates materials for a Product have been already bought, and subordinate knots are collected
It becomes that materials for assemblage in a warehouse didn't stand idle
How it is possible to reach desirable result?
What heuristics is better for using?
What is the strategy?
What options in a product should be?
What options of Optimizer?
Hi Timofey,
There is the operation lead-time offset in BOM details when you can control the offset for the component in relation to the start date for production of the superior assembly. Best regards/Tiemin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.