In the start of the import for SAPKH60019 and SAPKH60020, note 1540729 must be applied using ASU Toolbox. I have followed the steps for ST-PI 2008_1_* SP 04 of the note. In step 8, I have loaded the XML file using Tr. /ASU/START, following note 1000009. My problem is, what to do now. How and when I must execute the "Security Manual Follow-Up Steps" in /ASU/START?

Thanks in advance for your help.

Eduardo Barrios

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

My problem is, what to do now. How and when I must execute the "Security Manual Follow-Up Steps" in /ASU/START?

When - After applying Support Packages. For How - please read the Note 1000009 - ASU Toolbox 2008

Thanks

Former Member
0 Kudos

Hello,

Thanks for your help. My doubt about when, appears because note 1540729, says:

" We recommend that you execute the report in conjunction with importing the

Support Package because you cannot activate the XSRF protection at a later

time with the support of the ASU Toolbox described in the following

section."

It seems that it means, during the import of SP, not after the import.

Regards

Eduardo

Former Member
0 Kudos

Hello,

I thought ST-PI

For other SPs I think ASU tool transaction needs to be executed before SP upgrade. I never got an opportunity to experience this scenario but While working in SAP Release Upgrade (For e.g. 4.7 to Ecc 6 EhP4) we had to run ASU process both the times - Before the Upgrade and After the upgrade.

Thanks