Hi Everybody,
I have business Process where Fright Charges paying either Customer or Company. Which is I have maintaining this Field in Additional Data A tab (Header Level) in While creating Sales Order. After that Business Process is Delivery(VL01N)- Shipping (VTO1N)- Shipment Cost (VI01) Then VL02N- Picking and PGI. In the case of Customer is paying Fright Charges which is maintained in Sales Order in Additional Data A @ Header Level. But some time in this case user has doing PGI without performing Shipment (VT01N) and Shipment Cost (VI01).
In the above situation I want to prevent PGI without performing performing Shipment (VT01N) and Shipment Cost (VI01). If user
do this system should give the Error Massage PGI is not possible due to Shipment and shipment cost is Missing. How can this possible? What are the configuration is required? Kindly give me your valuable suggestions. Waiting for your reply.
Thanks in advence.
Regards,
Manzoor Ahmad
I believe this is not possible in SAP Standard.
You will have tp apply a User Exit in Delivery, which will check for Shipment Status as Complete & only then allow for PGI>
Hope this helps,
Thanks,
Jignesh Mehta
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks for your valuable answer. My has been resolved.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
you can control this with user exit which will control without the shipment will not allow the user to perform the PGI
Check this :MV50AFZ1
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.