Hi,
Whatever I change the period factor in Transportation Lane, the start date of SNP PR is the date which is corresponding to Wednesday, and end date of the order is the date that is corresponding to Thurday.
I would like to know why?
Note:
1) planned delivey time in production location master is zero
2) not use period factor in production location master
3) caculation rule in planning calendar is that workday is from monday to friday.
Thanks,
Quanyin
Edited by: Quanyin Su on Oct 11, 2011 9:55 AM
Hi,
Please check whether your lot size setting is weekly lot size ?
regards,
Manimaran M.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Can you check planned delivery time in ECC .iF planned delivery time maintinae din ECC then date will get calculated fromECC.
MJ
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.