Hi all,
I am asked to generate on report for reporting the comparison of the planned finished date and actual finished dates for quality notification both in terms of analytic, graphics and overdue days for notification closure .
Please advice how to use SAP to generate the Bar charts for such kind of data.
Regards,
Vivek
Hi,
Unless your requirement is too specific, all std. reports can be converted in to graphical forms like Bar charts etc.
Regards, KrishnaM