Budget/Actual Expenditures and commitments data

Former Member
0 Kudos

Hi

Could someone help me with the tables from where the data relating to the projects with total approved budget,expenditures ,commitments data can be pulled in ?

Thanks in advance for the help.

SE

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Check the RPSCO table with the WBS Element object number. You can filter based on value type field (41 stands for budget, 4 fro actual etc).

regards

Sreekanth

Former Member
0 Kudos

Hi

Thanks for your reply, it was really helpful.

One question I have is How to link the WBS element objetc number in RPSCO to the project definition in PROJ?

Thanks,

SE

Former Member
0 Kudos

Hi,

In PRPS tabe give wthe project number. This will give you all the WBS Element in the project and also this table has the object number (OBJNR) for WBS Elements. Take these OBJNR's and pass it to RPSCO.

Regards

Sreekanth

Former Member
0 Kudos

Thanks for you guidance .

SE