Hi All,
Is there any way or a transaction to change the "actual finish dates" in the network activities of one or more projects ?
Regards
sapmm
Hi
Actual finish date? No transaction available. Actual dates are derived based on confirmation of an activity.
You can use mass change functaionality for forecast finish date but not actual dates.
Regards,
PSR
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
If you are using CATS then actual dates will come from CATS.
What is the need to change actual dates by d way ??
Regards
Keshav
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
CN25 is to enter individual confirmations where you can post the actuals..
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
As stated by PSR, this is only possible via confirmations. Try CN27 for collective confirmations. This may help to change the end dates for a list of activities. However, you will have to provide other parameters for confirmations as well like start date etc.
Regards,
Ammar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.