on 10-07-2011 2:58 AM
What could be the possible reasons?
The order is for a procurement type E HALB...
If the planning strategy is not maintained, could it be the reason?
Edited by: tildveryn on Oct 7, 2011 10:23 AM
First you need to identify what schedule line category is flowing in your sale order.
Next go to VOV6, select that schedule line category and check whether the box "Req./Assembly" is ticked.
G. Lakshmipathi