Dear All,

I Have a problem with Create PO with Network. I must put the budget until the delivery date of PO. How to make so i put the budget in Document date in PO??

Thx.

Icuk Hertanto

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Dear All,

I have budget at Delivery date in Purchase Order/Requisition and sometimes we have problem with budget availability next year from contract date.

How can I change checking posting date to PO/PR creation date instead Delivery Date??

I check in customizing but I didn't found it.

Thx

Former Member
0 Kudos

I have budget at Delivery date in Purchase Order/Requisition and sometimes we have problem with budget availability next year from contract date.

How can I change checking posting date to PO/PR creation date instead Delivery Date??

I check in customizing but I didn't found it.

Former Member
0 Kudos

Hi,

Your query is not clear. Kindly elaborate.