In-house production with on-line publication and external procurement C5

Former Member
0 Kudos

Dear SAP Gurus,

I need to configure PPDS to immediate transfer in-house production orders but to have periodical transfer for external procurement, do you know how to do this?

Thanks and BR

Andre

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

May be your integration models for production and planned orders are inactived?

Please, check it.

Former Member
0 Kudos

Hi

Goto Spro-APO-supply chain Planning-PPDSGlobal setting-maintain global parameters and defaults-

Transfer to R/3 Inhouse Production- Always create transfer event

Transfer To R/3 External Procurement- Do not create transfer event.

To transfer external procurement periodicaly you can use /SAPAPO/RRP4 go to change mode and click on transfer order.

Have a small test from all angles before going ahead with this approch. As you need check whether changes to already transfered purchase requisition get transfered to ECC if not how you will identify such orders and send it to ECC.

May I know what is buisness reason for such requirement because I seen requirement to transfer inhouse production and external procurement only on conversion but heard of such requirement first time.

Regards,

Santosh

former_member197994
Active Contributor
0 Kudos

Indeed I've heard of such a requirement. At the moment I can think of using one of the

Exits, but how to change the transfer event of the EP orders? Best regards/Tiemin