Dear Gurus,
I originally posted this in PP and SD, however, it does now seem to be APO related.
Hence my posting here. Can you help? This is the question:
"How can we prevent that APO immediately creates a planned order when the purchase requisition is put in the system.
(apparently they set up the system as such that a flow then starts and automatically transforms the planned order into a production order).
We want to prevent APO to automatically create a planned order from the purchase req, we only want a planned order at a later stage, i.e. the finalised purchase order.
If a setting like this exists, can we activate this per plant?"
Thanks!
Hi,
Please check the events maintained in the planning procedure assigned to the product.
Best Regards,
Chirag
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello there,
The control that you mentioned can be maintained at a product level, which is more granular than what you have asked for. Refer to the PP/DS tab of the product master and you will find a filed for PP planning procedure, which determines various actions that PP/DS executes for a specifi type of event. There are standard planning procedures (procedures 1-9) and ofcourse you can configure your own procedures as well.
The configurations here define if your dependents requirements have to created immediately or just a planning file entry has to be created or a product heuristic has to be started immediately or no action has to be taken!
Refer to below link for more info:
http://help.sap.com/saphelp_scm70/helpdata/en/c1/147a375f0dbc7fe10000009b38f8cf/frameset.htm
Cheers,
Kalyan.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.