Hi Experts,
I am using DP81 for creating sales pricing.I am planning cost(unit costing) in version '1' and then running DP81 system throws message 'No expenditure item found'. But if i do cost planning(unit costing) in version '0' then i am able do the sales pricing.
So, my question is why system is not allowing to do sales pricing if i plan cost in version '1'?. It is client's requirement that he doesn't want to do plan cost in version '0' for quotation purpose .
please suggest some solution.
Thanks
Please refer below notes.. may be useful..
SAP Note : 212974
SAP Note : 940270
SAP Note: 1094018
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
what is the plan version in your DIP profile
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Virendera,
I did not use Version as a characteristic initially in DIP profile. But after your reply i tick the check boxes CharactRelevant and Mat.Determination for Version. And in last step of DIP profile i.e Criteria i put 001 in value field against version. But after doing all this when i run DP81 i have got the same message No expediture item found.
Please let me know if i am still missing anything in DIP profile.
Thanks.
Still waiting for your replies.
Edited by: SAP PS on Oct 5, 2011 10:57 AM