Creation of PR with MD01

Former Member
0 Kudos

Hi,

Somebody knows if exists some parameter that allows the grouping creation of PR with transaction MD01? In my customer, the MD01 creates one PR for each material

Thank you!

Accepted Solutions (0)

Answers (1)

Answers (1)

vasudevap_pushpalas
Active Contributor
0 Kudos

Dear !!!!!

I think the Possible Entry u can Make Individual/ Collective requirement = 2 Collective in MRP4

Also if you want all requirement to get add monthly or by weekly then it can be get instead through lot size

As in yours cases you want monthly then make MB in MRP1 view .Keep lot size MB.

This will create only one PR for the entire month.

Revert Back!!!!!

With Regards

Pushpalas

Edited by: pushpalas on Oct 1, 2011 2:29 PM

Edited by: pushpalas on Oct 1, 2011 2:36 PM

Former Member
0 Kudos

Hi Pushpalas. thanks for you answer.

I have changed the MRP parameter in the material Master, but it is still generating one PR for each material.

Do you know why?

regards

Former Member
0 Kudos

Create material via matmas. Only MDM can come to the rescue.

Install MDM. Create material there. Provide matmas for all SAP instances.