on 09-30-2011 12:53 PM
Hi,
This is the scenario:
When you approve a SC in SOCO a PO is "automatically" created. But this PO is created in status "Saved".
We need to create this PO in status "Ordered".
Do you know how?
I've tried to find some place to put a enhancement point in order to pass the parameter i_save to X, only for try, but i don't find the proper place...
Thanks in advance.
Hello,
(...)
When you approve a SC in SOCO a PO is "automatically" created. But this PO is created in status "Saved".
(...)
Don't understand... There is no workflow in SoCo, so you never approved a SC in SoCo.
In SoCo, you select SC items to create follow-on document.
(...)
We need to create this PO in status "Ordered".
(...)
I guess vendor assigned to PO created is a preferred vendor (partner '00000039') and not a fixed vendor (partner '00000019').
Check your implementations for BAdI BBP_DOC_SAVE or BBP_DOC_CHANGE_BADI.
Regards.
Laurent.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.