on 09-30-2011 8:46 AM
Hello
I have cretaed project with WBSE and Network Activities . Designed for Forward scheduling . The steps are as follows :-
1.After creating the Project Definition , system will provide start date i.e today's date.
2. After Creating Network activities with duration and providing relationships between the activities , then schedule the Project .
3. After scheduling the Project , end date of the project can be seen in the Project definition .
Issue is as follows :-
after confirming the activity , and reschedule the project , system is changing Project Definition start date as well as end date .
required start date should be fixed and end date should be changed according to confirmation of avctivity .
Can u pls suggest what settings are needed .
Regards
DMR
In customizing, goto Dates -> Date Planning in WBS -> Define Parameters for WBS Scheduling and ensure that the correct parameters have been maintained (specially llok at the indicator: Adjust Basic Dates) according to your requirement. Refer to SAP help on the node for further assistance.
Regards,
Ammar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi DMRAO,
Please verify the value that is maintained for field 'Plan.meth/basic' on the control tab of the project definition (Planning Dates). It should be Top Down (using this method whenever a project is saved the system automatically checks the dates within the project structure, if time scheduling is not consistent then the project cannot be saved).
Regards,
Ammar
User | Count |
---|---|
94 | |
11 | |
10 | |
6 | |
5 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.