Cost elements as summary at condition table

Former Member
0 Kudos

Dear experts,

I want to place a value of some cost elements (plan calculation) and some conditions (from condition table) as a result of a small calculation at one value field at the end.

I have found code (ABAP include) for calculate the needed conditions... but not how I can calculate (add) some cost elements from (plan) calculation.

Has anybody an idea?

Thanks a lot!

Accepted Solutions (0)

Answers (1)

Answers (1)

gomatheeswaran_palaniappa
Active Contributor
0 Kudos

Hi,

Are you referring to some cost conditions like EK01, VPRS etc in sales orders? If so, you can store the calculated value by placing Subtotal as B adjacent to the cost condition type in pricing procedure (Tcode V/08). The value will be stored at komp-wavwr.

Regards,

P Gomatheeswaran