on 09-29-2011 8:33 AM
I urgently need to configure an RA key to calculate WIP when project status is REL and COS when project status is TECO. Is it possible to achieve this with one RA key? I have configured my RA key to successfully calculate WIP at REL (based on actual costs) but I haven't been a ble to determine COS. What are the config steps please?
Try OKG3.
Go to expert mode ..There you should be able to configure the valuation based on the system status with the same RA key
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks for the response. Entries are:
RA Key with REL status:
RA type - F (WIP calculation on basis of actual cost)
Profit Indicator - M (With profit realization)
Valuation Basis - I (Actual Cost, Actual Revenue)
Plan Version - 0, Version f. sim. - 0, valuation level - Z, profit basis C.
RA Key with TECO status:
RA type - Z (Cancel Data of WIP Calculation and Results Analysis)
Profit Indicator - M (With profit realization)
Valuation Basis - I (Actual Cost, Actual Revenue)
Plan Version - 0, Version f. sim. - 0, valuation level - Z, profit basis C.
Final RA - X
When I run KKAJ for system status REL, WIP is calculated and posted upon settlement. My expectation is that when system status is TECO and I run KKAJ, COS will then be calculated and the accounting entries passed upon settlement? This doesn't happen. When I run KKAJ with system status TECO, no values are calculated even though revenue is posted to the sales order assigned to the project. Any ideas?
In TECO, system always consider cost of sales as actual . it ignores the planned cost at this time. You are already posting actual cost while in REL status with your current settings . that why you are not seeing any posting in TECO mode.
why do you want to post same actual in REL and TECO mode?
can you please provide me the process. i ean the cost and revenue part and what are you trying to achieve
This is the scenario, when actual costs are incurred, the clients want these actual cost to be posted as WIP provided they haven't yet delivered the project to their customer. Upon completion of the project they then want to move all costs incurred to cost of sales. What should the proper scenario be?
There are lot of settings involved.
Are you considering Planned cost too?
normally in REL status
RA Type : F
PI: M
Valuation: o
valuation level S
Profit basis: C
project structure A
in TECO
RA Type : Z
PI: M
Valuation: I
valuation level S
Profit basis: C
project structure A
in TECO system cancel the WIP and post actual
Hi,
You have raised a similar query in one of your threads before. You could have handled this in the previous thread.
Anyway, get in touch with your CO consultant for the configuration of the specified RA key. He/She should be able to help you.
Regards,
Gokul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.