Hi,

Can we have GRN as dynamic storage bin no, at time of GRN against the PO.

How this can be achieved via configuration.

Regards

Jena J

Accepted Solutions (1)

Accepted Solutions (1)

former_member189686
Active Contributor
0 Kudos

Hi, Jena

Please check the below configuration Path

SPROLogistics ExecutionWM-Activities--Define Requirement types

Here create new requirement type as Material docuement, MSEG-MBLNR,

Then go to

SPROLogistics ExecutionWM-Activities--Define Mvt Types

and assign the new requirement type against Warehouse no. and Mvt type 101.

And after this when u create GRN for PO it will have dynamic storage bin as your GRN no.

Hope it will help you.