on 09-28-2011 3:33 AM
Hi,
We are having following scenario.
We are creating the project in PS. Then creating the PM order & assigning
the order to WBS element.
We want to use the Estimation method of progress analysis. Hence we havedefined Estimation method as default measurement method (both plan &
actual )for following objects,
1. WBS element
2. Internal processed activity
3. External processed activity
4. General cost activity
5. Order (Other than Network)
For WBS element & all activities we are able to manually maintain planned
POC & actual POC in CJ20n.
But for PM order we are not able to manually maintain planned POC &
Actual POC.
Can you please let me know where we can manually maintain the planned &
actual POC for PM Order.
regards,
Pradip Shelke
> Can you please let me know where we can manually maintain the planned &
> actual POC for PM Order.
I do not think it is possible for order to use estimation method..
Please go for Cost / Time / Work proportional
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
111 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.