Hello Experts,

I would like to copy an entire Client from one system to another but the systems are on different ehp-levels.

The source-system is on ehp1 level while the target-system is on ehp4 level.

Are there any known problems that i should be aware of??

Thanks in advanced

Kalle Eismann

Accepted Solutions (1)

Accepted Solutions (1)

former_member182307
Contributor
0 Kudos

Hello,

I don't this this works. To my mind it's like performnig a client copy between 2 different releases.

The dictionnary should be slightly different so I don't think this works.

Here is a note from SAP about this :

Note 1398718 - CC:INFO-Client copy between different EHP'S

Best regards,

Steve.

Edited by: steve_78 on Sep 26, 2011 2:22 PM

Former Member
0 Kudos

So I need to do a system-copy and then patch the system to ehp4 first

Thanks anyway