Reverise transport from Prod to QA

Sriram2009
Active Contributor
0 Kudos

Dear All

We have three system BI landscapes. In that every the process chain are running for extraction. In that some of the major changes are doing in production Bi system. Is this any way we can sync the process chain from Production to QA system reveries transport? Kindly advice us

Regards

Sriram

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Technically reverse transport is possible but not a best practice.

Contact your BASIS team for the execution.

Regards,

Nick Loy

JPReyes
Active Contributor
0 Kudos

that some of the major changes are doing in production Bi system

You should not be doing development in your production environment, this goes against every logic of having a 3 tier system.

Productive system should be locked from changes for obvious reasons and changes should only come in as transport requests

Technically reverse transport is possible but not a best practice

Changes in the production system should be copied manually to the development system and retransported so version management is updated and consistency restored.

Regards

Juan

Answers (2)

Answers (2)

Former Member
0 Kudos

There are two options to do a reverse transport:

1) Copy data and cofiles of the source (PRO) server into target server(QUA), then import them using STMS.

2) Create a reverse transport layer temporarily and import the request.

Before choosing the option, you have to change your PRO client settings to allow the changes as recordable.

*I suggest to contact your BASIS team for a smooth execution

Regards,

Nick Loy

Sriram2009
Active Contributor
0 Kudos

Hi

Thanks for your support Nick & Juan

Could you pl tell me the steps which we need to follow?

Regards

Sriram