Dear All ,
After CIFFED BOM and Routing from ERP, PDS is not showing ACTIVITY and OPERATION (APO-PPDS).
It is only showing Components and Configuration.
Can any body guide to correct the same??
Regards,
NS
Please, delete the Resource from APO and transfer it again from ECC. That should solve "Resource XXXXX does not exist" error.
Additionally, please check that in the header of the BOM, the BOM Status is set to active and that in the header of the routing the status is Released (general).
After that, retransfer the PDS to APO and check if the activity went through.
Edited by: Tiago Furlanetto on Sep 26, 2011 4:56 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Check folllowing
1. Resource/Work centre has been cifed to APO and integration model for Work centre is active.
2. Check resource is created in APO and assigned to model 000
3. Check production version status in ECC (it should be green)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Vipul ,
I have Checked the folllowing
1. Integration Model for Resource/Work center is active on ERP side
2. Resource is created in APO and assigned to model 000
3. All production version status in ECC are green
I deleted the PDS IN APO (/SAPAPO/CULL_RTO_DEL ) and tried again to transfer using Curto_create.
Message "Resource xxxxxxxx does not exist" appearing and no PDS generation in APO whereas the Resource is available in APO and also assigned to Model 000.
It seems there is data inconsistency related to ECC and SCM and tried resolving using /SAPAPO/OM17 but no sucess.
Can you please guide further now??
Thanks ..
NS