Hi All, we are on EHP4 and we activated ECP at activity level in config "view to activate . Would appreciate any solution/inputs..
hope you have activated the business function OPS_PS_CI_1 in SFW5
and also activated the following in SPRO
Project System >> Costs >> Planned Costs >> Easy Cost Planning and Execution Services >> Easy Cost Planning >> Activate Planning for Network Activities with Easy Cost Planning
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Define Alternative CO version and Activate Multiple CO version for your controlling area in SPRO. Follow the path SPRO-Project System-Costs-Planned Costs-Easy Cost planning and execution services-Easy Cost PLanning-Define alternative CO versions & Activate Multiple CO version.
This should solve your issue i suppose.
Regards,
Gokul
Gokul/Abdul,we have activated the bus function in SFW5 as well as network planning for ECP. thanks everyone for your inputs. i think we are facing a unique situation where it's not getting triggered despite performing the prereqs. one thing like some of you advised, i didn't find any option on EHP4 to activate mutiple CO versions. can anyone confirm they have come across themselves on this version.. i saw quite a few notes on this forum and fellow professionals mentioning that but didn't come across the option on EHP4.
many thanks,
did you try report RCNPRECP
please try in sand box first..!!
SPRO >>> PS >> Costs >> Planned Costs >> Easy Cost Planning and Execution Services >> Easy Cost Planning >> Define Alternative CO Versions
SPRO >>> PS >> Costs >> Planned Costs >> Easy Cost Planning and Execution Services >> Easy Cost Planning >> Activate Multiple CO Versions
i tried both the paths you mentioned, but they aren't available in EHP4. the only option that's available at this path is 'Define CO versions for ECP'
Besides, we made some progress where we heard from SAP that we need to activate enhancement EA-PLM in SFW5. However, we are still weighing our options whether to go ahead with it as you can't revert back on this once activated. so, need more study on this to ensure there are no side effects by implementing this function.
thanks a lot for your involvement/inputs..
PSPM
Activating this function on EHP4 enables both the options alternative CO versions and multiple CO versions. note 1389108 gives more details about the same. Probably this would have been applied already in the environments where my other forum mates have tested/advised, hence the options were available already for them. Though we are yet to implement it in our environment, have been able to track the exact issue with assistance from this forum, and of course SAP
It's great to be on this forum. Thanks everyone for your participation.
PSPM
There are threads availabe which talks about ECP at activity level. Go through that you will find out what you are missing.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
104 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.