Dear Expert,
1. we create PO with account assignment category " N "
2. GR on this PO, now the parts consumed on the related network / activity automatcally. Stock is 0
3. CNS0 , at this time, we think the open quantity of this component for related network / activity should be 0 , but the showing qty is still reqirement qty.
What is the problem ?
BR , Shubin
If you plan the material on network activity these material will show in CNS0 for creating the delivery note. In your case you are not keeping project valuated stock and you have already consumed all the material. so nothing to deliver. The use of CNS0 is to handle project stock.