Hi All,

As per the EU customs, some of the customs offices in Netherland will

be changed on 25th Sep. as per the business requirement we would be

doing the upload of the new file from customs, we would like to have a

confirmation that if the new offices are created as new BP, what will

happen to existing offices, will the existing offices will be

automatically replaced or deleted ?

Is there any business implication if the existing offices are not

deleted.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hello Santosh,

Upload of changed files, which contain new customs offices, will create them as new Business parters.

Offices which are in the existing system but not in the new file WILL BE deleted - for this please check ( or ask a developer to check ) the program /SAPSLL/CUSTOFF_UPLOAD_PRE as this is maybe different for different GTS versions.

Actually the easiest would be just to try it in a sandbox enviroment ?

Regards,

Branislav Petricek

former_member215181
Active Contributor
0 Kudos

Hi Santosh,

You should probably check with your Data Provider, but my expectation would be that the existing Customs Offices would remain. If any have not been used, then they can be archived immediately; otherwise you will need to archive them after the corresponding Declarations have been completed.

Regards,

Dave