Plan cost transfer problem from Quotation to Project

Former Member
0 Kudos

Hi,

We are using BOS (Bill Of Service) functionality in SD. At Quotation creation we are using Easy Cost Planning under service tab screen. Also we are transferring Quotation line item cost to different WBS by using BOSPS01 T code. System is showing same cost in CJ20N Easy Cost Planning.

But problem is that it is not summing up at Project Definition level. Hence these cost plan value is not showing in any PS report. When we do the Easy Cost Planning from CJ20N directly then system is summing up at project definition & same values are flow in all PS report.

If some one have any Idea about this problem, please give your valuable inputs.

Regards,

AVI

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Please implement SAP note 1158702

Regards,

Amit

Former Member
0 Kudos

Hi Amit,

Thanks for your reply. I confirmed with my basis team that this note is already implemented in system but still we are facing this error.

If any one help in this regard that will be really appreciable.

Regards,

AVI