cancel
Showing results for 
Search instead for 
Did you mean: 

entering partner function code in Delivery after PGI

siva_vasireddy2
Active Contributor
0 Kudos

Hi all,

i have a requirement where in after PGI of delivery i need to change or enter a partner fucntion -contractor code number in VL02N.please help me.

Regards

Prasad

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Siva

Once PGI is done delivery process is over . U cant change partner function after doing goods issue .

input your datas before Good issue

regards

Arunkumar

siva_vasireddy2
Active Contributor
0 Kudos

Dear Arun,

you are right but there must be a way out,b-cos we are able to change partner fucntions in sale order even after Billing completed.

Regards

Prasad

jpfriends079
Active Contributor
0 Kudos

Hello

Do [Partner Determination|; for contractor in delivery document.

There are lot of material available for partner determination on web.

Kindly take use of that.

Regards

JP

siva_vasireddy2
Active Contributor
0 Kudos

Dear JP,

the partner determination is already done but the problem is after PGI the Partner Functions fields are in Display mode how can i put them in change mode.

Regards

Prasad