Hello Everyone,
How much time needed to upgrade SRM 5.0 to SRM 7.0?
How many resources are needed to upgrade SRM 5.0 to SRM 7.0? And for how long?
Regards,
Khushbu.
Edited by: Khushbu Brahmbhatt on Sep 20, 2011 9:13 PM
Hi ,
Minimum time frame is 10 months to 18 months.
Depends upon the customized objects.
SRM ABAP webdynpro resources required : 4 resources(minimum)
SAP EP -Enterprise resource --- 2 resources
SRM functional -- 2 resources (min)
Since testing is required extensively. Plan one more SRM functional..
Regards
G.Ganesh Kumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
...
Edited by: Trudy Southall on Jan 4, 2012 5:43 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.