on 09-20-2011 8:41 AM
Hi Gurus,
how can I close project with not zero WBSs? Client has a project wit not zero wbs a very old cost on wbs. Stores = wbs don`t exists no more and they can`t move the cost from wbs.
Could zou help me?
Thanks very much.
BR,
Martin
Hi,
Did you mean system let you delete the old WBS even though you had balance in it? Anyways, you can update CLSD status to rest of the WBS Elements in the project. And if reporting is your problem, then you will have to use a variant to exclude this one from the selection.
Regards
Sreekanth