Close project with not zero WBSs

Former Member
0 Kudos

Hi Gurus,

how can I close project with not zero WBSs? Client has a project wit not zero wbs a very old cost on wbs. Stores = wbs don`t exists no more and they can`t move the cost from wbs.

Could zou help me?

Thanks very much.

BR,

Martin

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Did you mean system let you delete the old WBS even though you had balance in it? Anyways, you can update CLSD status to rest of the WBS Elements in the project. And if reporting is your problem, then you will have to use a variant to exclude this one from the selection.

Regards

Sreekanth

Former Member
0 Kudos

Hi,

yes I want to give status CLOSE to project and all wbs even though I have balance in it.

I moved cost with Tr. KB15N to cost center and in CJI3 I have zero balance for wbs. But by closing wbs I have error KO115 Balance is not zero.

BR,

Martin