Hi,

While creating a sales order for different materials in partneters i give different end customers based on the material.

So now while doing the delivery i get an error saying that delivery split due to conflicting header data (Function ZC: Partner Number

I understood this error is because of different partenter function in the header and the item level but how to over come this i want to create a single delivery even if the parters are different at header and item level.

Is there any way out for this.

regards

rajesh

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member1190345
Active Contributor
0 Kudos

Hi Rajesh,

In order to create a single delivery for 2 diffrenet materials certain criteria needs to be fulfilled which could be as follows:

1. Sames Ship To party

2. Same Del Plant

3. Same Shipping Point

4. Same Del Date.

Hence basically system will not allow to create a single delivery if the Partners are different.

Thanks and Regards,

J Nagesh.

eduardo_hinojosa
Active Contributor
0 Kudos

Hi

See these notes

SAP Note 166397 - Delivery split according to customer field ZUKRL

SAP Note 546668 - FAQ: Delivery split when creating deliveries

Regards