Plan Driven Procurment - External Requirements

Former Member
0 Kudos

SRM 5.0

R3 4.6c

Classic

PDP

When transferrring requirements from R3 to SRM I am running into a problem. We have a design requirement that all MRP reqs that do not have a source of supply come in to SRM. The problem is, it seems SRM doenst distinguish between req types, so with the bbp_extreq_transfer program runs its bring over reqs that should be sourced via ME56 or ME59 in R3. I think the flag in T160EX is set for all req types that have no source of supply, thus the program transfer them to SRM. I need MRP reqs with no sourceo of supply to transfer, but other req types should not. Anyone have any experience with this problem? Hope I explained correctly. I feel I havent.

Thanks in advance,

Justin

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

In T160EX you need to assign profile (created in T160PR) for the material group and purch group combination. So if a PR gets created with this combination it will sent to external system while you run the program BBP_EXTREQ_TRANSFER or RPRSEL01.

If you want to deviate from this there is an exit BBPK0001.

Regards

Reddy

Former Member
0 Kudos

Thanks for the quick response. I have looked at BBPK001 and I beleive this will work.

Thanks Reddy (I'll asssign full points after testing)!

I'm open to other ideas? anyone?