Scenario: We have water as Pipe line material. We have activated 89 inspection type & user is creating manual Inspection lot for the same.

Since this is a Pipe line material, there will not be any PO, GR so no inspection lot at GR. We do the GI with 201-P against the cost centre & vendor.

So my requirement is that, can it be possible to somehow create the inspection lot at the time of above GI OR

Any other way to create the inspection lot apart from creating it manually by Inspection type 89?

Looking forward for the favourable reply

Thanks

Sachin

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Sachin,

For 201-P u can have GI inspection type 02.Again it is not a stock relevant like 89.

Regards,

Nitin

Former Member
0 Kudos

Hi Nitin

Thanks problem solved