How to see resource capacity on buckets in 5.0

Former Member
0 Kudos

Hello,

We were glad that there is a new feature in 5.0 to connect the business partners to buckets and then to point the role functions in customizing to capacity groups in a View called Supply. I have set everything up as mentioned in the help, config guide etc and ran the integration program /RPM/CAP_PLAN_INT just to be sure but I cannot seem to pick up any resource supply. The resource availability and role functions are entered and mapped to capacity groups.

The labor cost is calculated correctly, though.

Thanks again,

Paul

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

I was able to answer my own question again. I created a view with the Bucket Process set to Capacity assignment and now I can assign capacities to buckets. I expected this to happen after entering the same information when editing a BP (bucket, role function etc.) but I guess that is only for searching and not for assigning capacities.

I hope this helps someone else.

Paul Sheehan