Hi all,

I am wokring with SRM 7.01 and ECC EHP5.

I am creating a Global Outline agreement that is then distributed to ECC.

Then this ECC Contract is used in some purchase orders.

Where I see the relation of ECC Contract to the Purchase Orders?

I cannot see it in SRM nor in ECC.

Regards,

Ezequiel

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

You can see this against the GOA created in SRM.

But you should be using Central Contracts from SRM7.0 onwards.

Regards,

Nikhil

Former Member
0 Kudos

That´s correct.

Details are under position -- Release.

Thanks