I have a multimixed resouce, this resouce has 10 capacities. For example, if each machine produces 10 kg / h(kilogramas by hour) and i have 10. My max/hour is 100kg/h.
Now, i try to create a Plan. Order of 100kg. When SCM creates an Order uses only first machine, in our example needs 10 hours to produce the order.
Changing our resource config to Time-Continuos, same example needs 1 hour.
My question is:
Is there way to use this 2 methods? because our client needs changing the planning by order. And not for Resource.
Thanks.
Best Regards
Hello all.
There is a field called "Splitting" in ECC and it's goes to SCM in the PPM.
Is There way to turn this field in a variable?
Best Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.