Hi Experts,

We have an indent for material X with Qty 1200,Progressive monthly dispatch plan from customer for an Year.

Material X

Delivery Date Qty CumulativeQty Planned Actual Delivered Qty

01.01.2011 100 100 100

01.02.2011 100 200 50

;

;

;

;

;

If I could able to deliver Qty 50 only in month 01.02.2011, Undelired qty of 50 has to automatically distribute to remaining months .

Also wanted to get the report of Total Planned Qty, Actually Dispatched Qty and Remaining qty to be dispatched for the current month and whole Year. Please help me how can give solution to my client..

Thank You

Saravana

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

As pe rthe client requirement, this process is not allowed in standard SAP, in this scenario you have to use the user exit as mentioned below-

USEREXIT_MOVE_FIELD_TO_VBEP - Use this user exit to assign values to new fields at the level of the sales document schedule lines. The user exit is called up at the end of the FORM routine VBEP_FUELLEN.

Thanks & Regards,