Planned Cost and report S_ALR_87013542

Former Member
0 Kudos

Hi All,

In report S_ALR_87013542, under plan cost column for Cost Element 500060 a figure of 1000 USD appears.

In CJ41 the 1000 USD has been planned at WBS element ABC. Detailed planning per cost element has NOT been done.

Also in CNE5 this material cost of 1000 USD appears under a paricular network activity (under WBS element ABC) appears under 'Assignment tab' , field name "Mat.planning".

In Value Categories - Value category "500060 - Material Consumed" has been created and cost element 500060 has been assigned to it.

Question:

1) From where in report S_ALR_87013542 the planned cost is apparing under Cost Element 500060 ? From where the system determines/relates the planned cost to

cost element 500060 ?

2) Report S_ALR_8703542 - first column refer to 'Value categories' or 'cost elements' ?

Please share your views.Thanks!

Regards

Dev

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Dev ,

If you are using CJ40 for planning , S_ALR_87013542 report will come according to G/L assingned to material valuation class. Pl check whether you have assigned material in CJ20N or planned in CJ40.

S_ALR_87013542 report is showing cost element wise detail planning according to plannnig which we have do either in CJ20N or CJ40 or Easy Cost Planning Method.

Regards

Keshav