When viewing the overview list on the Project Management tab the "Person Responsible" and "System Status" fields are empty. When I go into a project both fields are filled.

This is a standard cProjects implementation, these are not custom fiels. Any ideas why they are not filled in the overview screen?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

These fields are updated thanks to the project's dashboard evaluation. Can you check if the evaluation is triggered at save for this project type (in customizing).

If not, you'll have to schedule a job with report: DPR_EVE_BATCH_DPO in order to evaluate the projects on a regular basis.

BR

Matthias

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi.

The dashboard need to be refreshed to reflect the changes mentioned. You can also refresh the dashboard using the 'Refresh' button in the lower right corner.