Cat2 - How can I time write in days instead of hours?

Former Member
0 Kudos

In cat2, the default is to time write in hours. is it possible to change this to days?

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Yes, use a activity type that has a UoM as Day or Work Day in your time sheet.

Regards

Sreekanth

Former Member
0 Kudos

In activity type master data, KL02. Go to 'output' tab, maintain 'Day' as 'output unit' , maintain the 'factor' like if your UoM is Hrs. So let's say 1 day= 8hrs. so keep output factor as 8.