hi PS gurus,

What is the purpose of selecting this option (Copy Detailed planning for cost elements)? What does it do?

Many ThanKs

MM

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

In case you have done detailed planning for your project you can specify whether you want to copy the detailed planning data using this check box.Planning done using cost elements is called detailed planning in PS. CJR2 is the transaction to do that. For more details you can hit F1 on the field and check.

Regards,

Gokul

Former Member
0 Kudos

Many Thanks

issue resolved