on 09-12-2011 10:35 AM
Dear all
I am trying to find a way to execute CN41 or CN41N and add the fields for Actual Costs, Budget Costs and Person Responsible based on a fiscal year and not cumulatively over the duration of the project.
Can you advise if there is a way to do this or to add additional fields for this requirement. For example we would need to view fiscal year 2010 and 2011.
Many thanks
PRG
Hi PRG,
Could you please review the below notes?
43493 Project information system: New fields in structures
522581 User-defined fields are not displayed
188663 Enhancing selection views and dynamic selection
Best regards,
Enrique
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.