on 09-12-2011 8:46 AM
Hi Experts
I am trying to do delivery from the Project in CNS0, but everytime i try to do the delivery the message occurs that "There are no deliveries for the chosen project".
i checked the sales order in whcih the Finished good is account assigned the very WBS through which i am trying to do the delivery.
Please let me know if i need to do any configuration or the steps to do the delivery from the Project. As in my current Project is a SAP PS-PP integration in which the raw material is procurred in PS and then it flows to PP for Planned orders and Production orders and all the Production activity is taken careoff in PP itself.
I attached the Finished good in one of my internal activity and created a reservation for the same and i wanted to do the delivery from there.
Experts i look forward for your advice
1) Carry out availability for check components to be delivered 2) ENsure that materials linked to network activity do not have backflush indicator., 3) WBS/Network is released.
Regards,
mahendra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Mahendra
I checked the points -
1) Carry out availability for check components to be delivered - how do i "Carry out availability for check components to be delivered". i checked the stock availability and it was available in mmbe as unrestricted use
2) ENsure that materials linked to network activity do not have backflush indicator., - i checked and it dose not have a backflush indicator
3) WBS/Network is released - It is released.
When i press the delivery tab on CNS0 it say the same message
anything else i need to see
I did maintain the availability check in opjk with the checking rule itself.
When i go to CN22 transaction: MENU > Edit > availabilty > Materials, it shows a message "All inspected material components available for network 500000000024".
Now i go to CNS0 and check the comonent tab first, where i can see that the comonent is available for delivery.... Now i check the 2nd tab of Deliveries. on clicking it on delivery a message pops up and displays that "There are no deliveries for the chosen project".