copying basic dates to forecast dates

Former Member
0 Kudos

Hi Experts,

I am using WBSE and activities in my project. I want to copy basic dates to forecast dates. But, when i am doing this in Edit>Reconcile date->Transfer basic dates to forecast dates. Then my Planning type in network header also gets change from Basic date to forecast date. which i don't want. I just want that my basic dates get copied to forecast dates , so that i can use forecast dates as my planed dates through the project and never change it. So, that i can always compare , basic dates, forecast dates and actual dates.

Thanks.

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member230675
Active Contributor
0 Kudos

May be you can try the following....

1) Edit>Reconcile date->Transfer basic dates to forecast dates.

2) manually change Planning type in network header from forecast date to Basic date.

Former Member
0 Kudos

i am not able change it ..it is not editable.