Hi Experts,
I am using WBSE and activities in my project. I want to copy basic dates to forecast dates. But, when i am doing this in Edit>Reconcile date->Transfer basic dates to forecast dates. Then my Planning type in network header also gets change from Basic date to forecast date. which i don't want. I just want that my basic dates get copied to forecast dates , so that i can use forecast dates as my planed dates through the project and never change it. So, that i can always compare , basic dates, forecast dates and actual dates.
Thanks.
May be you can try the following....
1) Edit>Reconcile date->Transfer basic dates to forecast dates.
2) manually change Planning type in network header from forecast date to Basic date.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.