on 09-12-2011 4:21 AM
Hi Experts,
We are using Estimation method for progress Analysis.
Following setting have been made for progress version,
Plan version : 0
EV Basis : 4 Cost Plan (active project, annual values)
POC weighting : 1 Cost plan (active project, total value)
planning type : Basic date
Early/Late : Ealiest possible
Reference:-
Actual mehod : ticked
Ref Plan method : ticket
We have manually given the 25 % in (Plan as well as actual) POC field of progress tab of WBS element.
Kept the POC weight of WBS element as BLANK.
After that executed CNE1 & then checked the following values in CNE5,
- Aggr. plan POC
- POC act.agg.
Both Aggr. plan POC & POC act.agg. are showing the value of 75% (3 times of 25%).
whereas system is properly calculating the BCWP & BCWS.
Please let us know why system is multiplying the POC by 3 ????
Regards,
Pradip Shelke
SAP note 189230 contains some information that you may find useful when troubleshooting within your progress analysis.
Hope it helps.
Regards,
Syed Ammar Zaheer
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.