on 09-11-2011 9:06 PM
Hello SOLMAN Experts,
I'm trying to activate BPM Business Process Monitoring and getting the following short dump:
Runtime Errors TIME_OUT
Short text
Time limit exceeded.
What happened?
The program "SAPLDSVAS_PROC" has exceeded the maximum permitted runtime without
interruption and has therefore been terminated.
Any advice please?
Thanks,
123
Hello,
For the time being (Temporarily), you can try to increase the parameter rdisp/max_wprun_time to some higher value and then try activation process. This parameter is I think 'dynamic' and so can be updated without system restart. You can verify this from rz11.
After you done, revert the value.
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
80 | |
9 | |
9 | |
7 | |
7 | |
6 | |
6 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.