In SNP how can I configure the following
Forecast consumption should occur when the product is allocated and not dispatched. There could be several days between allocation and delivery.
Sai
Hi,
Why don't you try with the strategy Planning with final assembly (Strategy 40 in ECC and 20 in APO)? In this strategy, the forecast will be consumed immediately after you enter the sales order, and even before doing the GI.
Regards,
Manimaran M.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sai,
Please refer the SAP Help on below link -
http://help.sap.com/saphelp_scm50/helpdata/en/6f/785e3f71e41e26e10000000a114084/content.htm
Hope this will help.
Thank you.
Satish.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
15 | |
4 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.