Hi all,

In SNP how can I configure the following

Forecast consumption should occur when the product is allocated and not dispatched. There could be several days between allocation and delivery.

Sai

Accepted Solutions (1)

Accepted Solutions (1)

m_manimaran
Active Contributor
0 Kudos

Hi,

Why don't you try with the strategy Planning with final assembly (Strategy 40 in ECC and 20 in APO)? In this strategy, the forecast will be consumed immediately after you enter the sales order, and even before doing the GI.

Regards,

Manimaran M.

Answers (1)

Answers (1)

satish_waghmare3
Active Contributor
0 Kudos

Hi Sai,

Please refer the SAP Help on below link -

http://help.sap.com/saphelp_scm50/helpdata/en/6f/785e3f71e41e26e10000000a114084/content.htm

Hope this will help.

Thank you.