Hi,
We are facing a unique case in ME2J, when we execute the report-ME2J (Purchasing documents at project level ) at WBS level which is assigned as account assignment in PO ( Accounti assignment category -Q ) and its showing the output report at WBS level and network level even though the network is not linked anymore in PO.
As per the std requirement/functionality, ME2J should show the output values only at WBS level not at both (WBS & Network ).
We not able to trace from where this network derived into ME2J report.
Any suggestions would be greatly appreciated.
Thanks in advance,
Risha
Hi,
Check the data entry profile you are using in ME2J. It must contain the check box "Include Hierarchy" checked.
Regards
Sreekanth
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I think your assumption is incorrect as ME2J is suppose to show all purchase documents related to project. So it will show all purch. documents related to WBS as well as networks.
If you want to see only Purch. Orders related to WBS or with acc assignment as Q. You can use MM reports where you have input option either as WBS or account assignment category.
Regards,
Mahendra
HI,
Please check your PR is created from PS through by assigning material component to activity. I this case activity is assigned to network and network is assigned to WBS. So you a/c assignment category in this PR is Q. And same PR whne you are covrting to PO then a/c assignment category is same as PR which is Q.
So in ME2 J you are getting the value against the netowrk.
Please check the source of generation of PR.
regards,