Shift Factor for late completion

Former Member
0 Kudos

Dear all,

Here i have a requirement

i have created a maintenance plan with cycle -10 days

Shift factor 80%

Tolerance 20%

Cycle start:22.08.2011

Scheduling period:30 days

Schedule calls were

Plan dates:

01.08.2011

11.08.2011

21.08.2011

But first completed on 04.09.2011 delayed by 3 days,

Plan date Completed date Act variance

01.08.2011 04.08.2011 3 Days

According to shift factor (80%) my next call will be 80 % of 10 days Ie) 8 days from completion date (04.08.2011) will be on 12.09.2011.

But i got next calls on 13.09.2011,23.09.2011

How system is calculating second plan date?

Somebody pls analyse it

Thanks in advance

R.A.Kiran

Accepted Solutions (0)

Answers (2)

Answers (2)

jgilliot
Newcomer
0 Kudos

Hello,

Is the tolerance or shift factor late completion sap is available on Multi-counter maintenance plan ?

Thanks

Former Member
0 Kudos

Calculation of shift factor is not based on cycle length, but based on delay. Delay is 3 days. 80 % of 3 days will be 2.4 days. By rounding up, the next calls have been scheduled by 13.09.2011,23.09.2011.

Check the link:

http://help.sap.com/saphelp_470/helpdata/en/3c/abb384413911d1893d0000e8323c4f/content.htm

Former Member
0 Kudos

Helpful answer

Thanks a lot

Kiran

Former Member
0 Kudos

Issue resolved