Dear all,
Here i have a requirement
i have created a maintenance plan with cycle -10 days
Shift factor 80%
Tolerance 20%
Cycle start:22.08.2011
Scheduling period:30 days
Schedule calls were
Plan dates:
01.08.2011
11.08.2011
21.08.2011
But first completed on 04.09.2011 delayed by 3 days,
Plan date Completed date Act variance
01.08.2011 04.08.2011 3 Days
According to shift factor (80%) my next call will be 80 % of 10 days Ie) 8 days from completion date (04.08.2011) will be on 12.09.2011.
But i got next calls on 13.09.2011,23.09.2011
How system is calculating second plan date?
Somebody pls analyse it
Thanks in advance
R.A.Kiran
Hello,
Is the tolerance or shift factor late completion sap is available on Multi-counter maintenance plan ?
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Calculation of shift factor is not based on cycle length, but based on delay. Delay is 3 days. 80 % of 3 days will be 2.4 days. By rounding up, the next calls have been scheduled by 13.09.2011,23.09.2011.
Check the link:
http://help.sap.com/saphelp_470/helpdata/en/3c/abb384413911d1893d0000e8323c4f/content.htm
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.