on 09-06-2011 4:56 PM
Hi all,
1. Is possible to skip inspection based on Qty, we would like to skip the inspection after receving 10000 qty from supplier
2. Is possible to skip inspection based on duration, we would like to skip the inspection after one year starting from date of first goods receipt
Please provide your valuable suggestions
Thanks & regards,
rajesh
No.
And No.
Sorry. not with standard SAP.
FF