strategy plan call horizon time same for monthly and weekly ?

Former Member
0 Kudos

Hi Sir,

As per my client requirement Strategy plan using for PM module.

In the strategy plan we are using weekly monthly,quarterly.in the strategy plan call horizon given 80%.

system giving all plans calling 2days before.

Actual

weekly-2days

monthly-6days

quarterly-18days.

but system not showing like this.

Where i can change the settings??.

Thanks,

Naresh Reddy Nandi

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

System takes the call horizon days of the lowest package to all other packages ..

I would suggest you to check this link

regards

pushpa

Former Member
0 Kudos

thank you for your response.

If any other solution is there(any enhancements..).

Thanks,

Naresh Reddy Nandi.

Former Member
0 Kudos

Hi Naresh,

Did u try with User exit :- IPRM0002 ?

Work Around :- Is to create a singly cycle plan for each package cycle ..thus Callhorizon will be applied for the cycle mentioned in the single cycle plan ..

regards